No trains run between Lewes and Three Bridges from 13 to 21 February 2027, the whole school half-term. Replacement buses run via Cooksbridge.
No trains will run between Lewes and Three Bridges for nine days in February. The railway north of Lewes and Brighton closes from Saturday 13 to Sunday 21 February 2027 for engineering work.
Network Rail announced the dates on Tuesday, three months ahead. Replacement buses will run instead, including a route from Lewes to Three Bridges via Cooksbridge and Haywards Heath.
The closure covers the whole of the East Sussex school half-term, which runs from 15 to 19 February 2027, and both weekends either side.
What runs instead
Network Rail lists these replacement bus routes for the nine days:
- Three Bridges and Lewes, via Haywards Heath and Cooksbridge
- Haywards Heath and Plumpton
- Lewes and East Grinstead, weekdays only
- Three Bridges and Brighton, calling at all stations
- Three Bridges and Haywards Heath
A direct train will still run between London Victoria and Brighton. It will be diverted via Horsham and Littlehampton, so journeys will take longer.
Network Rail says people travelling between the Brighton and Hove area and Gatwick Airport or London should use that diverted train rather than the buses. It has not said how long the diverted journey will take.
Train times on the coast lines to and from Brighton will also change. That covers the East Coastway, the line through Lewes to Newhaven, Seaford and Eastbourne. The revised times are not out yet. Network Rail says National Rail Enquiries and other journey planners will show the February train and bus times later this month.
What is being done near Lewes
The closure lets engineers do several jobs at once. Network Rail lists these on the routes through Lewes district:
- new rails at Plumpton
- new signalling and a renewed level crossing at Hamsey
- new signalling and a renewed level crossing at Spatham Lane, near Westmeston
- new rails through Clayton Tunnel, and a new conductor rail from the tunnel to Preston Park
- renewed track, switches and crossings at Keymer Junction, near Wivelsfield
Further north, the work also includes earthworks at Haywards Heath cutting and Balcombe’s Stamford rock cutting, and structural work in Balcombe Tunnel.
Lucy McAuliffe, Network Rail’s Sussex route director, said the route was “one of the busiest rail corridors in the country”.
“We know closing the railway is an inconvenience, but the extended closure over February half-term 2027 allows us to deliver a huge volume of work at once, avoiding repeated disruption across multiple weekends or during the busy summer season,” she said.
Before February: Sunday 29 November
The line between Lewes and Three Bridges also closes for one day on Sunday 29 November. Buses run between Lewes and Three Bridges via Cooksbridge and Haywards Heath that day. The details are on our Lewes roadworks and travel page, which we update each week.
What it means for you
- Commuting to London that week: allow much longer. From Lewes you will need a bus to Haywards Heath or Three Bridges, or a train to Brighton for the diverted service to Victoria.
- Flying from Gatwick over half-term: Network Rail advises the diverted Brighton train rather than the buses. Leave extra time.
- Travelling from Plumpton or Cooksbridge: both stations are on bus routes for the nine days.
- Newhaven and Seaford: trains to Lewes and Brighton are on revised times, not cancelled. Check before you travel once the timetable is published.
Network Rail’s helpline is 03457 11 41 41.